[London 1] Tier III Storage Maintenance
Scheduled Maintenance Report for Xperience
Completed
The scheduled maintenance has been completed.
Posted Jan 30, 2019 - 00:00 GMT
In progress
Scheduled maintenance is currently in progress. We will provide updates as necessary.
Posted Jan 29, 2019 - 20:00 GMT
Scheduled
On Tuesday January 29th between the hours of 20:00-00:00 our engineering team will be performing hardware maintenance on our Tier III storage platform in London 1. Whilst this work is taking place, backup services (Veeam, CloudBerry & OnApp) and Tier III services such as FTP, iSCSI, CFS/NFS will be unavailable for up to 1 hour.
Posted Jan 22, 2019 - 14:24 GMT
This scheduled maintenance affected: London 1 Cloud Platform.